Case Studies

30/09/2011

Belleville School Annex

Belleville School Annex

Wandsworth Borough Council entrusted Langley with two bespoke challenges for the roof refurbishment works at Belleville Primary School.

Firstly, a decision had been made to remove the existing internal drainage system on the flat roof areas between the slated pitched roofs. This meant that Langley had to ‘reverse design’ the falls to run towards the newly devised external gutters.  

This was achieved using Langley’s Parafoam Ultra Tapered Insulation and Parafor Solo cap sheet to welted drip detailing at roof perimeters.

The second challenge was the replacement of numerous rooflights on both the flat and pitched roofs. Langley designed individual structural rooflights, including pyramid ‘top hats’, for the pitched areas and bespoke modular units for the flat roofs.

The resulting installation handled by Langley approved contractors Breyer Group plc, is an outstanding showcase of the new system design.

 

Main System Products:

Parevapo SBS

Parafoam Ultra Tapered Insulation

Adepar JS

Parafor Solo

 

 

Download the full Case Study

Further Information

Find out more about our roofing services by calling us on 01327 704778 or emailing us at [email protected]

Other Case Studies

13/05/2020

King George Hospital

Contractor:  Inspire Contracts Ltd Size:  1,300m² Aging roof estates and reduced maintenance budgets have resulted in reactive maintenance becoming the only feasible way for many trusts to operate. For this reason, roofs demand attention only when a problem... > Read more

29/04/2020

RAF Waddington

CLIENT: Amey Property Services CONTRACTOR: Morello Services Ltd SIZE: 3,200m² Having reached the end of its life expectancy, the existing roof at RAF Waddington, Lincolnshire, had begun to experience issues, including water ingress. After a roof condition survey... > Read more