Case Studies

08/12/2016

Kingsbury High School

When London’s largest high school approached specialist consultants Capita PCC to refurbish its facilities, Langley was called upon for the roof refurbishment element. Langley’s in-depth survey and report highlighted complications with the schools current drainage system and inefficient insulation.

The roof’s unusual design meant that every roof had to be individually designed due to the variation between the roofs and drainage issues each roof presented.

The resulting Langley specification overcame these variations correcting the drainage on each roof area and enabling the school to retain more heat with improved insulation throughout.

The first phase of the refurbishment, totalling 5,000m², was completed by Langley approved contractor Breyer Group PLC to an exacting high standard and within timeframes. 

 

Main System Products:

Adepar JS

Paradiene [35] S R4

Parevapo SBS

Parafor Solo GS

 

Download the full Case Study

Further Information

Find out more about our roofing services by calling us on 01327 704778 or emailing us at [email protected]

Other Case Studies

22/04/2021

Netherthorpe Academy

CONTRACTOR: Everlast Waterproofing CONSULTANT: Eddisons SYSTEM USED: TA-25 Flat Roofing System Netherthorpe Academy has made best use of Condition Improvement Funding (CIF) to optimise the health and safety of an estate that combines aesthetic heritage spanning back 450... > Read more

22/04/2021

Radford Primary School

CONTRACTOR: Cambridge Flat Roofing Premier Roofing Construction CONSULTANT: Barker Associates SYSTEM USED: TA-30 Flat Roofing System Langley Structures Striptiles Water leaking into the classrooms alerted the management team at Radford Primary Academy to the need to... > Read more