Ottershaw Infant School

Langley was selected by Surrey County Council to assess their roof and produce a comprehensive condition report and specification. Inadequate drainage of the existing roof system caused significant internal leaks with ponding water adding additional stress to the building.

Langley recommended stripping the existing covering to expose the structural deck and install a TA-20 warm roof system with tapered insulation to improve the thermal efficiency of the roof.

Ottershaw Infant School fully utilised Langley’s free survey service, condition report and bespoke design service. Langley Approved Contractor, West End Group, was chosen to undertake the installation within a challenging 6 week period out of term time.

The work was successfully completed to a high standard on time for the staff and students’ return in the new term.

On completion, Surrey County Council and Ottershaw Infant School have complete peace of mind their roof is covered by a Langley independent, insurance backed guarantee for 20 years.

 

Main System Products:

Adepar JS

Langley Primer

LangStik SF

Paradiene [35] S R4

Parafoam Ultra

Parafor Solo GS

 

Download the full Case Study

Further Information

Find out more about our roofing services by calling us on 01327 704778 or emailing us at [email protected]

Other Case Studies

13/05/2020

King George Hospital

Contractor:  Inspire Contracts Ltd Size:  1,300m² Aging roof estates and reduced maintenance budgets have resulted in reactive maintenance becoming the only feasible way for many trusts to operate. For this reason, roofs demand attention only when a problem... > Read more

29/04/2020

RAF Waddington

CLIENT: Amey Property Services CONTRACTOR: Morello Services Ltd SIZE: 3,200m² Having reached the end of its life expectancy, the existing roof at RAF Waddington, Lincolnshire, had begun to experience issues, including water ingress. After a roof condition survey... > Read more